高级检索

深地高地压高天井大断面扩孔技术研究与应用

Research and application of large cross-section hole reaming technology in deep-earth high shaft with high ground pressure

  • 摘要: 某铅锌矿回采工程、开拓工程目前逐步向深地转移,需在超千米深高地压特殊条件下进行井下回风系统建设。建设主要包括地表井口相对0 m标高以下−1 106 m中段、−1 046 m中段和−1 276 m中段的3条垂直天井。施工采用反井钻机对井筒施工成形直径2 m的小断面井筒,再按照回风设计要求,结合高天井刷扩技术对井筒进行大断面扩孔至4 m,井口配套工程包括稳车硐室施工和稳绞系统设备的选定,施工过程采用Flac3D软件对井筒进行应力评估并对应力集中部分进行补强支护。通过理论计算、工艺技术及配套设备的运用,千米深高地压高天井扩孔施工技术在该铅锌矿的成功应用,为国内深地高天井大断面扩孔工程提供了技术理论与实践依据。

     

    Abstract: A lead−zinc mine back-mining project and a pioneering project are now facing a gradual shift to the deep earth, facing the special conditions of over 1 000 metres deep and high ground pressure for the construction of the underground return air system. The construction mainly includes three vertical shafts in the middle section of −1106 m, middle section of −1 046 m, and middle section of −1 276 m below the relative 0 elevation of the surface wellhead. The construction of the shafts was carried out using a backhoe drilling rig to form a small section of 2 m in diameter and then combined with the high-shaft brushing and reaming technique to ream the shafts to a large section of 4 m in accordance with the design requirements for the return air. The supporting works for the shafts included the construction of winch chambers and selection of equipment for the stranding system, and during the construction process, the shafts were evaluated by stress assessment using Flac3D, and reinforcement support was carried out on the stress-concentrated portions of the shafts. Through the above theoretical calculations, process technology, and supporting equipment, the successful application of reaming construction technology in high shaft with high ground pressure for kilometre depth in the lead−zinc mine has provided a technical theory and practical basis for the large cross-section hole reaming construction in deep-earth high shaft in China.

     

/

返回文章
返回